PROJECT AUTHORIZATION |
PACKET ID: PMT-OT6Z |
CONTRACT ID |
EMARS PROGRAM CODE |
AUTHORIZATION NO: |
221341 |
9455503C 9455502C 9455501C |
94555 |
10 |
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID |
PROJECT ID NUMBER |
FEDERAL PROJECT NUMBER |
6 YR PLAN ITEM NUMBER |
6 YR PLAN ITEM PARENT NUMBER |
|
|
0791011
|
03-80001 |
3-.- |
PROJECT TYPE |
PROJECT LENGTH |
NUMBER OF BRIDGES |
SYSTEMS |
MINOR WIDENING |
MI |
|
|
PROJECT PHASE
&
RESPONSIBILITY |
PLANNING |
DESIGN |
RIGHT OF WAY |
UTILITIES |
|
|
|
|
CONSTRUCTION |
TITLE DEEDED TO: |
MAINTENANCE |
OTHER |
|
|
|
|
FUNDING & TIME
ACCOUNTABILITY |
PARTICIPATING AGENCIES |
FEDERAL |
FHWA |
STATE |
KYTC |
LOCAL |
|
OTHER |
|
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER |
PHASE |
FUND |
PROGRAM |
FEDERAL FISCAL YEAR |
STATE FISCAL YEAR
|
FEDERAL APPR
CODE |
CURRENT FUNDING REQUEST |
3-80001.2 |
C |
1200 |
FD52 |
2022 |
2023 |
BDG6,Y240 |
$9,284,837.00 |
3-80001.2 |
C |
1300 |
FD52 |
2022 |
2023 |
|
$300,000.00 |
3-80001.2 |
C |
1100 |
FD52 |
2022 |
2023 |
|
$1,478,482.00 |
CURRENT FUNDING REQUEST TOTAL: $11,063,319.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE |
TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING |
$0.00 |
DESIGN |
$1,550,000.00 |
UTILITIES |
$1,860,000.00 |
R/W |
$1,620,000.00 |
CONSTRUCTION |
$11,063,319.00 |
NON-HIGHWAYS |
$0.00 |
|
Total: $16,093,319.00 |
THIS AUTHORIZATION PROVIDES FEDERAL BUILD GRANT CONSTRUCTION FUNDS TO COVER LOW-BID AND CEI. |
|
Project Approval Recommended By:
James Ballinger 9/19/2022 |
Signed and Approved by:
Jim Gray 9/20/2022 |
ITEM NO. |
COUNTY |
DIST |
FACILITY NAME
|
ROUTE |
LENGTH |
03-80001.20 |
TODD
|
3 |
US 79 |
US 79 |
MI |
Replace and Widen the bridge over CSX Railroad and realign the KY 346 intersection. (2020BOP)(BUILD)(TO BE LET WITH 3-10010 & 3-80100) |